12/03/2013 – 12/08/2013
We needed to reschedule the cabinet delivery that we initially scheduled before thanks giving due to the delay in tile delivery (it actually worked out because of such a bad imperfection of the concrete sub floor. We needed to spend a lot of unplanned time flattening the floor…), and not it costed us… the installation clue wasn’t available for the first week of December, and we needed to wait one week without doing much before we could finish everything else…
12/09/2013
12/10/2013
12/11/2013
I also installed the rest of base board tiles, but forgot to take pictures….
12/12/2013
Ash, one of our chinchilla was not acting like usual, so we took her to vet, along with Mocha (the other chin) just for check up. We came back with Antibiotics, now facing a huge challenge of how we gonna feed it to Ash… anyhow, when we got home, I was pretty much ready to pass out from lack of sleep… so no work done…
12/13/2013 – 12/22/2013
Between SWMBO’s business trip and our chinchilla in vet, I was slacking off and didn’t do much till the 12/21 weekend… During the week, I painted the bedroom side wall, installed cabinet knobs, and a lot of cleanups. We also did touch up on other doors around the house since we got open paint anyways!
So, please continue to the tour of our new bathroom!
Hi,
just recently bought a craftsman air compressor, looks like yours. but without any labels.
do you mind telling me what model is yours? i am trying to find a manual and some parts for it.
Hi,
just recently bought a craftsman air compressor, looks like yours. but without any labels.
do you mind telling me what model is yours? i am trying to find a manual and some parts for it.
thanks,
John
alllaji@gmail.com
sorry being late, but will check the label tonight.
Edit: I tried to find a model number and just couldn’t find it… sorry
Good job
大変よく出来てますね
友達に感謝